Sandhya Gupta tells more about she solved delayed sprint issues by backing up her facts with data.

Problem

I was working in a team that was using waterfall model within a sprint. All development has to be completed followed by testing. Side effect of this was stories would get pushed out of sprint because testing could not be completed within the sprint timeframe even though development was complete. This was a continuous trend across sprints. Sprint demos were held with larger groups including business teams and they were losing confidence in team's ability to deliver as agreed upon.

Actions taken

Collected data for last 6 months to how average number of stories that were pushed out because of this symptom. Got buy-in from team and leads on if we could try a different approach to re-building credibility. Testing will begin as story begins for development. All use cases will be identified and automated using stubs. As soon as a story is completed, another engineer will pick it up for testing manually or in automated fashion. This story will now go through "show and tell" in daily scrum. This distributed the task of testing throughout the sprint improving odds of completing the story within the sprint.

Lessons learned

Provide data to the team to challenge if current approach is working or not. Identify small changes that will help the team in a positive way.

Discover Plato

Scale your coaching effort for your engineering and product teams
Develop yourself to become a stronger engineering / product leader


Related stories

Hiring a Data Team With a Stubborn Manager

24 May

Liz Henderson, an Executive consultant at Capgemini, shares her experience hiring a data team with a manager who was difficult to work with.

Managing Up
Building A Team
Conflict Solving
Hiring
Data Team
Liz Henderson

Liz Henderson

Executive consultant at Capgemini

Managing Remotely: Balancing Team Cohesion and Focus Time

26 May

Jonathan Belcher, Engineering Manager at Curative, explains how to balance team cohesion and individual focus time, tapping into his experiences of working remotely for seven years.

Remote
Micromanagement
Meetings
Internal Communication
Productivity
Psychological Safety
Performance
Jonathan Belcher

Jonathan Belcher

Engineering Manager - Patient Experience at Curative

Navigating Disagreements When It Comes to Priorities

9 May

Pavel Safarik, Head of Product at ROI Hunter, shares his insights on how to deal with disagreements about prioritization when building a product.

Innovation / Experiment
Product Team
Product
Dev Processes
Conflict Solving
Internal Communication
Collaboration
Convincing
Strategy
Prioritization
Pavel Safarik

Pavel Safarik

Head of Product at ROI Hunter

The Necessary Structures of Time Management

14 April

Suryakant Mutnal, Engineering Manager at PayPal, discusses the importance of time management and the necessary structures in order to create internal consistency.

Goal Setting
Managing Expectations
Remote
Deadlines
Productivity
Roadmap
Prioritization
Performance
Suryakant Mutnal

Suryakant Mutnal

Engineering manager at PayPal

Why Documentation Is the Key to Success

6 April

Henning Muszynski, Head of Frontend at Doist, promotes his ideas on how documentation ensures consistency, efficiency, and standardization.

Alignment
Collaboration
Productivity
Hiring
Team Processes
Henning Muszynski

Henning Muszynski

Head of Frontend at Doist

You're a great engineer.
Become a great engineering leader.

Plato (platohq.com) is the world's biggest mentorship platform for engineering managers & product managers. We've curated a community of mentors who are the tech industry's best engineering & product leaders from companies like Facebook, Lyft, Slack, Airbnb, Gusto, and more.